Nov. 27, 2023
Today we will talk about commisioning of Low-voltage power conveying system
Installation and Commissioning
Equipment Installation
Carry out open-case inspection of equipment, propose handling suggestions to damaged or missing parts
Mark out or pop up cross curve as per the layout chart
Hoist and put the track in place as per the cross curve position
Splice tracks into an entire section by junction plate
Align and level the track, ensure space and track parallel
Install safety sliding cable and transducer box
Hoist drive trolley and driven trolley to the track, push the trolley back and forth, ensure the trolley runs smoothly
Install brush system and connect electric wires
Fix the track on the ground after all tracks and equipment are installed
Carry out a preliminary maintenance to the equipment
The equipment and distribution box must be connected by licensed technician
Equipment Commissioning
Open key switch to switch on the power
Insert the key to switch on the remote power
Place pipes in the trolley by lateral conveying system, convey workpiece back and forth on whole the track at a different speed, observe the whole process and check whether functions are normal
Load at least 10t to the trolley and observe whether the trolley can work normally
Notices about debugging:
The trolley must be powered off in case that lateral conveying system is working;
Lateral conveying system must not enter into the trolley track in case that the trolley is moving;
Stop and check immediately in case of equipment shaking, pause or abnormal noise during moving forward and backward, remove faults and continue debugging
Finish the following operations and switch off the main power after equipment commissioning is completed:
Unload workpiece
Trolley stops at a proper position